Case Study | College of Occupational Therapists
Project Overview
Morse Consultants was appointed by the College of Occupational Therapists to project manage the refurbishment of its headquarters in London and to perform the health and safety role required as CDM Co-ordinators.
Morse Consultants split the works into three different stages – the temporary relocation to a serviced office, including lease review, space planning and dilapidations (Phase 1), the strip out of the property (Phase 2) and the refurbishment and roof renewal works (Phase 3) which was completed in January 2011.
Morse was involved at project inception through to final completion by establishing the client’s brief and working with architects and other consultants to produce a detailed specification. This included obtaining competitive tenders for the contract works and producing and managing the project budget to refurbish the existing upper floor offices and ground floor meeting and lecture spaces.
Services
DesignProject ManagementPlanning Supervision
Client: College of Occupational Therapists
Property: 106-114 Borough High Street
Contract: Building Refurbishment
Industry Sector: Commercial
Contract Value: £2 million
Location: Central London
Duration on site: 20 weeks
Case Study | College of Occupational Therapists
Project Overview
Morse Consultants was appointed to manage the re-roofing of the College of Occupational Therapists’ London headquarters building.
The project involved assessing appropriate roofing materials and methods of installation, due to access restrictions and confined areas of work; producing detailed specifications and obtaining competitive tenders for the contract. The project also involved co-ordination with mechanical contractors to remove and relocate roof plant and included for enclosing the majority of the roof top plant in a custom-designed permanent steel profiled sheet housing.
Services
DesignProject ManagementPlanning Supervision
Client: College of Occupational Therapists
Property: Borough High Street
Contract: Re-roofing and Ancilliary Works
Industry Sector: Professional Body
Contract Value: £95,000
Location: Central London
Duration on site: 8 weeks